46 Smart-UPS® VT 10-40kVA 400V Site Preparation and Installation Manual 990-2283
Floor Anchoring (Option)
Use the two transport brackets that secured the UPS to the pallet during transport for floor
anchoring.
Align the 4 holes in the bottom angle of the Floor Anchoring Bracket on either side of the UPS
to the pre-drilled holes in the floor.
Front Panel
Front Panel
Note
Floor anchoring is an option. If your installation does not require this option, proceed to
“Front Panel Installation” on page 45.
Note
Floor anchoring procedures are identical for both 352mm and 523mm UPS Enclosures.
See “Floor Anchoring Preparation” on page 14 and install a minimum of 4 anchors on
each Enclosure (minimum size: M8) where shown, following the specifications provided
by the manufacturer.
1
0
/100Base-T
Probe