InfraStruXure System - Installation and Start-Up 13
Join the PDU, UPS, and XR Battery Enclosures
1. Move the PDU, Symmetra PX UPS, and XR Battery Enclosures into position, aligning the holes in
the adjacent side panels.
2. Level the PDU, Symmetra PX UPS, and XR Battery Enclosure by using a level and adjusting the
leveling feet on each enclosure.
3. The following enclosures will need to be attached, refer to the graphic below:
An adjacent PDU and UPS
An adjacent XR Battery Enclosure and UPS
Adjacent XR Battery Enclosures
psx0023a