Installation ProceduresRoute and Attach Overhead Wiring
990-1467C InfraStruXure System – Service Manual – Installation and Start-Up 43
Route and attach power cables to equipment racks
If you ordered overhead wiring, connect the prewired power cables of the InfraStruXure PDU as follows:
1. Install the Shielding Troughs, Shielding Partitions, and Cable Ladders so that you can route power
cables from the PDU to the NetShelter VX Enclosures.
For installation instructions, see page 39.
2. Find the numbers that indicate the enclosure to which each power cable will supply power. These
numbers appear on the roof of the PDU where the power cables exit, and on the ends of each power
cable.
Note: The enclosures are not numbered. Consult your APC InfraStruXure Configuration
Build-out Tool to determine the enclosure associated with each power cable.
3. Beginning with the power cables for the enclosures farthest from the PDU, run each power cable
within the Shielding Trough along the row and, if necessary, across one or more Cable Ladders to
the enclosure to which it will provide power.
Note: Ensure that the L21-20 twist-lock connector at the end of each power cable always lies
on top of any longer power cables in the Shielding Trough.
4. Connect the appropriate power cable to APC power management equipment in the enclosure in one
of the four following ways:
For single-feed devices without redundancy: attach a power cable directly to a Rack PDU
installed in a NetShelter VX Enclosure.